Unlike general construction reports, an MEP report must account for complex subsystems, including:
| Trade | Priority | Planned Activities | | :--- | :--- | :--- | | | High | Start VRF piping if units arrive. Complete Level 5 FAHU wiring. | | Electrical | High | Start pulling conductors for Levels 1-2. Install Light fixtures Level 3. | | Plumbing | Medium | Complete Roof RWP. Start Level 5 restroom rough-in. | | All | Critical | Clash resolution meeting for Level 6 ceiling space (Wed 8 AM). | mep work progress report sample
Include high-quality, dated photos of completed work, particularly for hidden services (underground/concealed). Unlike general construction reports, an MEP report must